Feb 2 2026 West Side Project Update

Dear Sea Dunes Owner,

The demolition phase of the Westside Project on the 6th floor is anticipated to be completed today.

The tentative demolition schedule for Floors 5 through 1 is as follows:

5th Floor: Wednesday, February 4 – Thursday, February 12
4th Floor: Friday, February 13 – Monday, February 23
3rd Floor: Tuesday, February 24 – Wednesday, March 4
2nd Floor: Thursday, March 5 – Friday, March 13

1st Floor: TBD

Please be advised that elevated noise levels are expected throughout the demolition phase of the project.

We appreciate your patience and cooperation as the project continues to advance.

Kind regards,
Amelia Island Management